Our Refurbishment.
DYRSL has been the vibrant entertainment hub at the heart of our Northern Beaches community for more than 85 years.
While we embrace tradition, we’re also proud to set a new standard – we continuously progress, and we strive to do better tomorrow than we did today.
In July 2025, our Development Application to further improve the food, beverage and gaming offering for the community and for our current and future members, guests, and staff of DYRSL was approved.
Kicking off in early 2026, the first phase of the refurbishment will see the arrival of a brand-new café, Botanica. Once completed, we will then start works to move our Pittwater Road entrance to allow for easy access to our Bistro, enhance and increase the size of our popular Tastes of Asia restaurant and refurbish our current gaming room.
We appreciate your flexibility and understanding regarding these changes and look forward to updating you with further information.
If you have any questions, please email info@dyrsl.com.au
DYRSL has been the vibrant entertainment hub at the heart of our Northern Beaches community for more than 85 years.
While we embrace tradition, we’re also proud to set a new standard – we continuously progress, and we strive to do better tomorrow than we did today.
In July 2025, our Development Application to further improve the food, beverage and gaming offering for the community and for our current and future members, guests, and staff of DYRSL was approved.
Kicking off in early 2026, the first phase of the refurbishment will see the arrival of a brand-new café, Botanica. Once completed, we will then start works to move our Pittwater Road entrance to allow for easy access to our Bistro, enhance and increase the size of our popular Tastes of Asia restaurant and refurbish our current gaming room.
We appreciate your flexibility and understanding regarding these changes and look forward to updating you with further information.
If you have any questions, please email info@dyrsl.com.au
January and February 2026
Work is underway! Site preparations began on Thursday 8 January and demolition is now in full swing.
- Site sheds installed on Hawkesbury Ave
- Demolition of carpet, ceilings and stairs of The Gallery
- Demolition of external garden bed to make way for the new alfresco area of Botanica
- Battery House kitchen exhaust relocated in order to accommodate Botanica’s new roof
- Walls erected ready to be waterproofed in preparation for the roof removal in the coming weeks, ensuring the site remains watertight