On 23 March 2020, the Australian Government initiated an industry-wide shutdown of all clubs. As this was not extended to the building industry, both Boden Projects and Hutchinson Builders continued with the redevelopment.

Reception and Porte-cochere
The driveway and entrance was shut so all tiling of the Porte-cochere could be completed. The lower exit turned into an entry/exit during this time.

Carpark
All major structural works were completed, essential services in the basement and both lifts installed.

Battery House
The first stage of Battery House was completed!

All the furniture, pool tables and large TV were delivered, and the glass opening roof is working and ready to be used. A few fixtures and fittings have been delayed due to COVID19, and will be installed when they arrive.

The hoarding in the foyer has been removed and we were able to see the entrance in all its glory for the first time!