Progress / February 2020.

Reception and Porte-cochere
All is going according to plan with the new reception area roof completed and the glass installed.

Works on the porte-cochere is on track with the first stage set to be completed at the end of April.

Carpark
Two of three major concrete slab pours required to connect Bistro to Match Bar have been completed, with the third pour scheduled for March.

Works continue to take place underground as electrical, hydraulic and mechanical services well underway. The lift shafts are complete with the lift scheduled to be installed in March.

Battery House
Battery House is nearing completion as the bar and kitchen framing, stainless-steel works and equipment have all been installed. Bodens have completed the ceiling, and are now installing joinery items as they arrive on-site. Landscaping has commenced and will continue into March.